From plot to house
Between 105-135 days from signing the contract to handover.
The steps
You tell us where you are building and what area
The county, the approximate area and the number of storeys. We send you the price estimate based on these.
Site visit and firm quote
We check access for transport and assembly, the slope of the plot and the position of the utility connections. After the visit you receive the firm quote.
Contract and deposit
30% of the value
On signing, 30% is paid. From that moment the execution design of the frame goes into production.
Production and transport
15-45 days production · 45 days transport
The frame and the kit are made to measure. On proof the goods have left the factory, 60% is paid.
Assembly and handover
45 days
Our team assembles the frame, the envelope, the services and the finishes. The last 10% is paid after completion.
The foundation
The most common source of delays
If the foundation is built by you, it follows our drawing and is inspected before delivery. It is the most common source of delays.
The foundation is not included in the price per square metre. You can build it yourself or we can build it, as a separate option. Either way it follows our drawing, because the position of the anchors and the flatness determine whether the frame can be assembled without corrections on site.

From the factory to the house


When you pay
30%
On signing the contract
60%
On proof the goods have left the factory
10%
After assembly is complete