From plot to house

Between 105-135 days from signing the contract to handover.

The steps

  1. You tell us where you are building and what area

    The county, the approximate area and the number of storeys. We send you the price estimate based on these.

  2. Site visit and firm quote

    We check access for transport and assembly, the slope of the plot and the position of the utility connections. After the visit you receive the firm quote.

  3. Contract and deposit

    30% of the value

    On signing, 30% is paid. From that moment the execution design of the frame goes into production.

  4. Production and transport

    15-45 days production · 45 days transport

    The frame and the kit are made to measure. On proof the goods have left the factory, 60% is paid.

  5. Assembly and handover

    45 days

    Our team assembles the frame, the envelope, the services and the finishes. The last 10% is paid after completion.

The foundation

The most common source of delays

If the foundation is built by you, it follows our drawing and is inspected before delivery. It is the most common source of delays.

The foundation is not included in the price per square metre. You can build it yourself or we can build it, as a separate option. Either way it follows our drawing, because the position of the anchors and the flatness determine whether the frame can be assembled without corrections on site.

The ground floor of a steel frame house, after assembly

From the factory to the house

The production hall: panels and studs ready for delivery
The interior of a steel frame house, with the window openings prepared

When you pay

  1. 30%

    On signing the contract

  2. 60%

    On proof the goods have left the factory

  3. 10%

    After assembly is complete